tabriz oil refinery company hotel

 Project specifications
 project name construction of tabriz oil refinery company hotel
 project site sareyn
 Name of Employer tabriz oil refinery company
 main contractor almas tooba construction company
 The contract start date 2013/08/06
 Contract completion date 2014/06/05
 Duration and type of contract price list – 10 month
 Area – floors – structures square meters – 9 floors – concrete structure
Physical progress – Rials

facade of the building

completion of southern

completion of sleeper wall

project site visit

project specifications sign board

enclosure and entrance of the building

southern facade of the building

southern and western facades of the building

portal of the building

southern and western facades of the building

Dormitory of Mohaghegh Ardabili University

 Project specifications
 project name Execution of dormitory construction operations of Mohaghegh Ardabili University 
 project site Ardabil
 Name of Employer Mohaghegh Ardabili University 
 main contractor  Tooba Diamond Construction Company
 The contract start date 1397/08/15
 Contract completion date 1398/05/15
 Duration and type of contract 9 months – Comprehensive Circular
 Area – floors – structures 4230.86 square meters – 5 floors – metal structure
Physical progress – Rials (20.346.562.111): Physical: (48%) – Rials

Execution of the project skeleton

Execution of the project skeleton

Construction of project columns

View of the foundation and placement of the base plate

View of the foundation and placement of the base plate

View of the project skeleton

View of the project skeleton

Assembling parts of the project skeleton

Assembling parts of the project skeleton

Execution of the project skeleton